Field Note Completeness Checker

Checks field notes for station, backsight, instrument height, date, operator, units and CRS.

100% FreeRuns in your browserBasic
Method
Header

Date

Operator / booker

Job or site

Instrument and serial number

Weather / conditions

Setup

Station occupied recordedcritical

Orientation / backsight check observedcritical

Instrument height recordedcritical

Target / prism height recordedcritical

Closing check observed

Record

Units stated (m, degrees/gons)critical

CRS / datum notedcritical

All readings booked

Sketch and comments

Pages numbered

Readiness

Not ready

0 of 15 applicable items assessed (0% complete). Completeness is not readiness.

Critical items not passed

  • Station occupied recorded
  • Orientation / backsight check observed
  • Instrument height recorded
  • Target / prism height recorded
  • Units stated (m, degrees/gons)
  • CRS / datum noted

Still to assess (15)

  • Date
  • Operator / booker
  • Job or site
  • Instrument and serial number
  • Weather / conditions
  • Station occupied recorded
  • Orientation / backsight check observed
  • Instrument height recorded
  • Target / prism height recorded
  • Closing check observed
  • Units stated (m, degrees/gons)
  • CRS / datum noted

Records stay on your device as files you choose to save. The page keeps nothing.

This records what you checked and the evidence you noted. It does not verify the readings or replace field QA.

How the method works

Assessed is not the same as ready
Illustrative method
Assessed is not the same as readyFive checklist items, all assessed; one critical item failed. The assessment bar is full while readiness shows not ready.Instrument and units recordedPassSetup and target heightsPass★ Orientation checkFailDrone sectionN/A — reason givenSketch and notesPassAssessed 5 of 5ReadinessNOT READY — ★ critical failed
Every item has been assessed (5 of 5, 100 %), but the critical orientation check failed, so the record is NOT ready. Completeness counts assessed items; readiness needs every critical item to pass, no unresolved blockers, and a reason for each N/A.

Fixed example values for illustration — not your result.

Before you rely on this: First-pass guide only. Verify safety-critical or regulated work against the relevant standards, your project requirements and a qualified professional.

Tip: Enter any known values to calculate the remaining results.

Designed to run locally in your browser. Tool inputs are not intentionally stored by Zerdly unless stated otherwise.